BUILDTAKEOFF
HOME/CONCRETE/How Many Bags of Concrete for a 24×40 Slab?
Pole Barn Foundation • Verified Takeoff Spec
10% Standard Job-Site Safety Waste Included

How Many Bags of Concrete for a 24×40 Slab?

Direct Engineering Answer:

A 24×40 concrete slab poured at 5 inches thick requires ~16.3 cubic yards (or 734 eighty-pound bags / 978 sixty-pound bags) including 10% waste. Because this exceeds 2.5 yards, ordering ready-mix truck delivery (~1.7 loads) is typically 40% cheaper and saves hours of manual labor.

Primary Volume: 16.3 cu yd
80 lb Bags: 734 bags (80 lb)

Interactive Workstation & Complete BOM

Reset to Blank Hub →
BT-CONC-1048•Oct 15, 2026•Concrete Flatwork & Slabs

24x40 Slab Material Takeoff

01

Project Dimensions & Specs

Client-side reactive engine. Adjust parameters to recalculate quantities immediately.

ft
ft
in
Standard Thickness Presets:
Safety Waste Allowance:
02

Takeoff Schedule Summary

40×24×5"
ItemQuantityUnitEst. Cost
Ready-Mix (4000 PSI)16.3yd³$2,364
↳ Bag alternative73480-lb($4,771)
#4 Rebar Grid (12" OC)11520' sticks$1,668
Crushed Stone Base (4")18.26tons$639
10-Mil Vapor Barrier2roll(s)$270
Estimated Material Takeoff:$4,998 – $6,386
Subcontractor Flatwork Labor (~$1.35):~$6,747
Estimated Project TotalTurnkey materials + installation
$11,745 – $15,007
Interactive CAD Plan View
Scale: Dynamic Proportional
40 ft24 ft5" SLAB
#4 Rebar @ 12" O.C.
Crushed Base Incl.
Logistics: Ready-Mix (~1.7 truckload)
Advertisement • Sponsor
Complete Job-Site Bill of Materials (BOM)

Material Takeoff & Accessory Checklist

Click any unit price to customize for your local supplier costs.

Markup:
Sales Tax:
← Swipe to view all 6 columns →7 Line Items
Item / SpecificationCategoryQuantityUnit PriceTotal Est.Supplier / Order
Ready-Mix Concrete (4000 PSI)
Delivered via transit mixer truck, includes 10% safety overage
primary16.3 cu yd$2,608Local Supplier
#4 (1/2") Grade 60 Rebar (20 ft Sticks)
Grid reinforcement spaced 12" on-center both ways
accessory115 pieces (20')$1,668Home Depot
Rebar Tie Wire (Pack of 500 loop ties)
16-gauge bar ties for intersections + manual tie twister
fastener3 packs$60Amazon
Heavy Duty Rebar Chairs (2" - 3" height)
Maintains proper concrete cover above ground
accessory120 units$114Local Supplier
Crushed Stone Base (#57 or 3/4" Crusher Run)
4" compacted sub-base for drainage and stability
accessory18.26 tons$767Local Supplier
10-Mil Heavy Duty Polyethylene Vapor Barrier
10' x 100' roll, prevents capillary moisture ingress into slab
accessory2 rolls$270Home Depot
1/2" x 4" Foam Expansion Joint Strips
Perimeter expansion buffer for sidewalks, footings, and walls
accessory3 rolls (50')$66Local Supplier
Values update live with local price adjustments. Click unit prices to match your quotes.
Calculated Grand Total
$5,553
Engineering Methodology

Calculation Mechanics: Concrete Slab & Sub-Base

Formulas adhere to ASTM standards, ACI 318 guidelines, and standard construction estimating practice.

\ ext{Volume (cu yd)} = \ rac{\ ext{Length (ft)} \ imes \ ext{Width (ft)} \ imes \ rac{\ ext{Depth (in)}}{12}}{27} \ imes (1 + \ ext{Waste \%})

Step-by-Step Derivation Breakdown:

  1. 1Convert depth to feet: 5 inches ÷ 12 = 0.417 ft.
  2. 2Calculate raw slab volume: 40 ft × 24 ft × 0.417 ft = 400.00 cu ft.
  3. 3Convert to cubic yards: 400.00 ÷ 27 = 14.815 cu yds.
  4. 4Apply 10% safety allowance for uneven subgrade and form deflection: 16.3 cu yds total.
  5. 5Calculate 80-lb pre-mixed bags: 16.3 cu yd ÷ 0.0222 cu yd/bag = 734 bags.
  6. 6Calculate #4 rebar grid @ 12" on-center: 115 pieces (20ft rods) = ~2300 linear feet.

Field Inspection & Trade Best Practices

  • For driveways and slabs taking vehicle loads, 4000 PSI concrete at 5" minimum thickness with #4 rebar is recommended over unreinforced 3.5" flatwork.
  • Pouring over a compacted 4" crushed gravel sub-base prevents slab settling, frost heave, and cracking.
  • Place control joints at intervals no greater than 2.5 to 3 times the slab thickness in feet (e.g., maximum 10-foot spacing for a 4" slab).
Verified Commercial Subcontractor Network

Need a Licensed Subcontractor to Build This?

Request competitive estimates from insured, pre-screened Concrete & Masonry trade contractors near your job site. Real quotes based on your exact calculated takeoff volume.

Free & No Obligation Licensed & Insured Rapid Dispatch Response
Verified trade network. Zero spam guarantee.
Concrete Takeoff
16.3 cu yd$4,998 - $6,386

Frequently Asked Questions for 24×40 Slabs

How many 80 lb bags do I need for a 24x40 slab?

You will need approximately 734 bags of 80 lb concrete mix. This accounts for a standard 10% waste and spillage buffer.

How many 60 lb bags for a 24x40 slab?

If using 60 lb bags, you will need approximately 978 bags. 1 cubic yard requires 60 bags of 60 lb mix.

How much rebar is needed for a 24x40 concrete slab?

With a standard #4 (1/2") rebar grid spaced 12 inches on center in both directions, you need approximately 115 sticks of 20-foot rebar and 1025 tie points.

How much gravel base is required?

A recommended 4-inch crushed stone sub-base requires ~18.26 tons (13.04 cubic yards) of #57 gravel or crusher run.